14
Why does nobody talk about the day-long wait for concrete slab moisture tests? It throws off every timeline.
3 comments
Log in to join the discussion
Log In3 Comments
the_evan1mo ago
Our moisture meter just sits there for a full 24 hours. I mean, it totally kills any schedule you had. It's the worst.
5
the_hayden1mo ago
In my experience, waiting a full day for readings is brutal for project timelines. You basically have to build in a buffer for every single test, which adds up fast. Take that with a grain of salt, but it's a real schedule killer.
1
wyatt51326d ago
Man, that's the truth. @the_hayden, you hit the nail on the head about the buffer. It's not just one day, it's the domino effect on every other task waiting on that data. Have you found any tricks to work around that wait, or is it just a hard stop on progress until the meter finishes?