My anchor tenant's "simple" sign swap turned into 14 weeks at my strip mall in Toledo
I figured replacing one 12 foot pylon sign at my 6 unit strip center off Airport Hwy would run maybe 3 weeks, but the city made me pull a full site plan review because the new sign was 3 inches taller than the old one. Fourteen weeks and $2,900 in permit fees later (plus two rounds of engineering stamps) we finally got the panel up, and I lost a nail salon tenant who walked over the mess. What's the dumbest little detail that dragged out a build out for you, and did you bill it back to anyone?
Three inches. That's it, three inches and the city acts like you're building a skyscraper. We ate the cost, but I started adding a permit cushion to every build out after that.