Unpopular opinion: my sub's paperwork packet blew up the day before the inspection, and the fix was a single printed calendar
Last Tuesday afternoon, 24 hours before the city inspection at our 12-unit job in Columbus, my sub sent over a closeout packet missing three fire-rated sealant certs and a wet signature page. I had checked the submittal log on Monday and everything showed green, so I almost lost it (and I did, a little, in my truck). What saved me was something dumb: I printed a one-page calendar of the last 10 days of the schedule and taped it to the trailer wall, with every open item written on the day it had to clear. Turns out two of the certs had been sitting in a field guy's email inbox since the previous Friday, nobody flagged them. The calendar forced me to call that guy by name instead of sending another group text into the void. We got the packet stamped at 9:40 the next morning, which was 20 minutes before the inspector pulled up. I am now weirdly attached to that paper calendar, which feels like a step backward for a guy who lives in Procore. Anyone else had paperwork almost sink an inspection, and what actually stopped the bleeding for you?