My punch list hit 340 items on a 12,000 sq ft build and I froze
Wrapped up a tenant buildout in Boise and the walkthrough list came back at 340 items, way more than the 80 or so I budgeted for in the schedule. Half of it was paint touch up and door swings, but it still blew my closeout timeline by 9 days and the owner was not happy. Do you guys build a punch buffer into the schedule up front or just eat the delay when the list blows up like this?