Why does nobody talk about how much a good site log saves your butt
Everyone in this field acts like the daily site log is just paperwork for the inspector, and that bugs me. On a 14 unit job in Macon last year I pulled up my notes from a Tuesday and settled a concrete shortfall claim in about 20 minutes. The GC was sure we poured 18 yards, my log showed the pump ticket and the 16 yards we took off the truck. Most folks skip it or fill it in a week late. What do you all put in yours, and does anybody besides the old timers still keep a paper one?