Hot take: my sub skipped a compaction test on a 4,200 sq ft slab in Reno and I'm not sure if I should've made him pay to tear it out | Construction Management - Librear
Hot take: my sub skipped a compaction test on a 4,200 sq ft slab in Reno and I'm not sure if I should've made him pay to tear it out
He poured the slab Tuesday morning without waiting on the density report, and now I've got a 2 day hold while a third party reruns the tests. Half my crew says dock his pay for the delay since he cut the corner himself, but my PM says we eat it because the spec sheet never spelled out who books the inspector. What's the norm on your jobs when a sub skips a required test and the cost lands on someone, do you back charge or just move on?